Submission of Letter of Intent |
Minimum of 30 days prior to applications submission (six month
validity from date of receipt). |
Minimum of 30 days prior to applications submission (six month
validity from date of receipt). |
Submitted in conformance with published schedule for type of
project under review. Good for only one review cycle. |
|
Submission of Application |
After 30 days has lapsed and no later than six months after the
department’s receipt of Letter of Intent. |
After 30 days has lapsed and no later than six months after the
department’s receipt of Letter of Intent. |
Submitted in conformance with published schedule for type of
project under review. |
|
Application Screening |
Within 15 working days after application submission. |
Within 15 working days after application submission. |
Within 30 days after application submission. |
|
Applicant Response
(Applicant
may request the screening & response activity be conducted a
second time.) |
Within 45 days of receiving department’s request for additional
information.
(Additional responses to screening letters will be accepted up
to 10 days after the notice of Beginning of Review.) |
Within 45 days of receiving department’s request for additional
information.
(Additional responses to screening letters will be accepted up
to 10 days after the notice of Beginning of Review.) |
Within 30 days of receiving department’s request for additional
information. |
|
Formal Review Period
(Formal
review begins on fifth working day after applicant’s request to
begin review, or the department declares the application
complete.) |
A total of 90 days
First 35 days open to general public comment and conducting a
public hearing if requested.
Last 10 days open for applicant/ interested persons rebuttal
statements submitted during first 35 days of public comment
period
Last 45 days exparte period. Department is preparing
written analysis and decision. |
A total of 50 days
First 20 days open to general
public comment.
Last 10 days open for
applicant/ interested persons rebuttal statements submitted
during first 20 days of public comment period.
No
public hearing conducted on projects qualifying for expedited
review.
Last 20 days exparte period. Department is preparing
written analysis and decision. |
A total of 135 days
First 60 days open to general public comment and conducting a
public hearing if requested.
Last 30 days open for applicant/ interested persons rebuttal
statements submitted during first 60 days of public comment
period
Last 45 days exparte period. Department is preparing
written analysis and decision. |